+20 11 00 289 896|+966 53 646 4828|info@extramile-egy.com
← All articles

Actual vs Budgeted Project Cost: How Contractors Track It in Real Time

Actual vs Budgeted Project Cost: How Contractors Track It in Real Time

Short answer: To know whether a project is making money before it ends, a contractor needs three numbers per cost code: the budget, the actual cost so far, and the commitments already made (purchase orders and subcontracts not yet invoiced). Add an estimate of cost to complete, and you get a forecast margin you can act on. In Odoo, each project is an analytic account, each cost is tagged with a cost code, and budgets sit alongside actuals in the same report.

Most contractors discover a loss-making project at the end, when the final accounts are closed. By then the money is gone. The goal of job costing is to see the problem in month three, not month eighteen.

The four numbers that matter

The four numbers that matter
ItemMeaning
BudgetThe planned cost per cost code, from the tender or the execution budget
ActualCosts already incurred: materials issued, labour, equipment, subcontractor invoices, expenses
CommittedPurchase orders and subcontracts placed but not yet invoiced or received
Cost to completeThe engineer's estimate of what remains to be spent

Forecast final cost = Actual + Committed + Cost to complete (for the uncommitted remainder). Compare it with the contract value, including approved variations, to get the forecast margin.

Set up cost codes that match how you work

Cost codes should follow how your engineers think about the work, not only how accountants classify expenses. A practical structure:

  • Level 1: cost type: materials, labour, equipment, subcontractors, site overheads.
  • Level 2: work package: excavation, concrete, finishing, MEP, etc.

Keep it simple enough that site staff choose the right code every time. A detailed structure that nobody uses correctly is worse than a simple one.

How do you make the numbers real-time?

  • Purchases: every purchase order carries the project and cost code, so commitments appear immediately.
  • Materials: issues from site stores post to the project when they happen, not at month-end.
  • Labour: timesheets or payroll allocations by project.
  • Equipment: internal rates per day or hour charged to projects.
  • Subcontractors: progress invoices posted against the project.

The monthly project review

  1. Update cost to complete with the project engineer.
  2. Review the largest overruns by cost code.
  3. Check unbilled work: executed but not yet in a progress invoice.
  4. Agree actions: claims for variations, cost control, re-sequencing.

Frequently asked questions

Can we import our tender budget?

Yes. Budgets can be imported from Excel by project and cost code.

How are shared costs, like head office, handled?

Head office costs usually stay outside project cost, or are allocated at a fixed percentage. Decide this policy once and apply it consistently.

Can project managers see their own projects only?

Yes. Access rights can limit each manager to their projects.

See your projects' real margins

ExtraMile's construction solution on Odoo gives contractors live cost and margin per project.

Book a construction demo or message us on WhatsApp: Egypt · Gulf

This article was drafted with AI assistance and reviewed and edited by the ExtraMile implementation team.